Week of July 21, 2017

Prince of Wales Campus

Roofing work is in the final stages for the West Wing of Charlottetown Centre and Adult Education section of Montgomery Hall. Remaining work for Montgomery Hall is the metal fascia at the roof edge. For Charlottetown Centre the final layer of roofing is currently being installed then the metal fascia will be installed. There is about 2-3 weeks of work remaining.

Lintel replacement and repointing of masonry is complete for the Charlottetown Centre. The final piece of work for the masonry contractor is at the east and west wing entrances. For these three areas the deteriorated curved archway is being removed and replaced with new exterior insulation finish system (stucco looking).

Installation of the West Wing windows is near completion. The new windows for Samuel’s Campus Store and the Florence Simmons Performance Hall are set to take place the second week of August. All other remaining windows are set to be installed in the next couple of weeks.

Our summer painter has been busy at the Prince of Wales Campus. Many classrooms on campus have been given a fresh coat of paint.

Eight washrooms at the east Wing of Charlottetown Centre are being renovated. The work will include new flooring, new paint, new toilets and sinks, and new toilet partitions. We are working hard to complete the work as soon as possible, however, it is likely that the washrooms will not be ready at the beginning of the school year.

New porcelain tile flooring is also underway for many Holland College locations across the island. At the Prince of Wales Campus new flooring will make its way to several classrooms at both Charlottetown Centre and Montgomery Hall Adult Education.

Week of June 19, 2017

Prince of Wales Campus

Roofing work continues for the West Wing of Charlottetown Centre and Adult Education section of Montgomery Hall.

Masonry work is progressing well at the West wing. The major restoration work at the Grafton Street side of the West Wing is near completion.

The window effort for Charlottetown continues. The final touches for the East Wing windows are underway and the remainder of the Early Learning Centre windows will be installed after business hours. Installation of the West Wing windows will start this week.

Painting work last week and this week include Charlottetown Centre West Wing rooms 204, 207, 202 229 repair damaged sections of walls and repaint. As well, the hallway area outside 20w and 21w was painted last week.
Cleaning of the radiators continues at Montgomery Hall. To date the Adult Education wing is complete as well as level two, three and four of the Administration wing. The ground floor of the Administration wing will be complete this week.

Week of June 15, 2017

Prince of Wales Campus

Holland College campus in Charlottetown gets $4.6 million in upgrades. Click here for the full story.

Week of June 12, 2017

Prince of Wales Campus

Roofing work is starting this week. The work will include roof replacement of the Adult Education section of Montgomery Hall and most areas of the West wing of Charlottetown Centre. Contractor Evolution Roofing will mobilize on the site Monday, June 12. The roof work is expected to take 3-4 weeks.

Masonry work is progressing well at the West wing. The contractor is approaching the Kent Street end of the building.

The window effort at the East Wing is nearing completion. The Contractor expects to be complete of the East Wing at the end of June. The first work at the West Wing will be the replacement of the Florence Simmons Performance Hall windows.

Painting work this week includes The President’s Office (285 Kent Street) and SOPA building at 275 Kent Street.

Cleaning of the radiators continues at Montgomery Hall. Later this week we expect to start radiator cleaning of the Culinary Institute of Canada.

Week of June 5, 2017

Prince of Wales Campus

Masonry work continues at the West Wing. The work required facing Grafton Street is more extensive than some other parts of the building and will require more time.

The window effort at the East Wing is nearing completion. The Contractor expects to be complete of the East Wing at the end of June. The first work at the West Wing will be the replacement of the Florence Simmons Performance Hall windows.

Painting continues at the Centre for Community Engagement. This week’s schedule includes classroom 312, the dance studio and touch ups in the gym.

Cleaning of the radiators continues at the Prince of Wales Campus with Sam now focused on the Adult Education space of Montgomery Hall.

Week of May 29, 2017

Masonry work continues at the West Wing. The Contractors are working away at the Grafton Street side of the West Wing and coming up Weymouth Street.

The window effort continues at the East Wing. The windows facing the Early Learning Centre are installed and the staging has been removed. Once the planned shed building is placed, the exterior play space will be back in business.

Painting last week focused on the walking track of the Centre for Community Engagement. This week Spenser is working away at the hallways of the CCE.

Cleaning of the radiators continues with Sam working away at the East Wing of Charlottetown Centre.

Week of May 22, 2017

Masonry work continues at the West Wing. The Contractors are making good progress with both of the courtyard sections well underway.

The window effort continues at the East Wing with the windows at the Early Learning Centre their primary focus.

Our painter has been busy. He started two weeks ago. Last week he painted all the risers of the stairs at the Centre for Applied Science and Technology. This week he has moved to the Centre for Community Engagement. The first painting work was the risers of the stairs. He will focus the next few days on the Walking Track and hallways.

Cleaning of the radiators began last week. She began in the East Wing focusing on rooms where there is other work, namely window replacement, going on at the same time.

Week of May 15, 2017

It has been a busy few weeks at Charlottetown Centre. Masonry work and window replacement projects are well underway. The Early Learning Centre has closed the exterior playground during the month of May for the construction activity.

The weather has not been overly cooperative but West Masonry Ltd. Has been able to make significant progress. They started at the East Wing the latter part of April. To date all of the lintel work for the East Wing has been completed. As well, much of the masonry repointing is complete. Remaining masonry work includes installation of brick (at lintels), repointing, and washing the brick. The masonry work for the East Wing is expected to be complete by the end of next week (May 19). The masonry Contractor plans to start work at the West Wing late this week.

Regarding the windows, installation has begun at the East Wing. For the remainder of the month of May the window contractor will focus their efforts on the windows related to the Early Learning Centre exterior playground.

As noted previously, please keep windows closed during the construction activity.

There is roof replacement work scheduled for the West Wing of Charlottetown Centre. Evolution Roofing was the successful bidder and the work is scheduled to start the second week of June. Evolution Roofing will also be replacing the roof at the Adult Education section of Montgomery Hall.

We have hired a painter for the summer months. He started this week with some painting projects in Charlottetown Centre. In the coming weeks he will likely be in most buildings of the Prince of Wales Campus.

Starting next week, we have hired someone to clean the radiators at Charlottetown Centre. This initiative will improve the efficiency of the heating system.

Some other projects include:

  • new LED lights to be installed at most buildings
  • mechanical infrastructure upgrades including new roof top mechanical air handling equipment will replace aged equipment Charlottetown Centre
  • sprinkler work Charlottetown Centre
  • renovated washrooms for the East Wing of Charlottetown Centre
  • electrical infrastructure upgrades
  • new flooring in some areas
  • upgrade the building management system for the Centre for Applied Science and Technology

CCEWing
Photo of Charlottetown Centre East Wing

Construction Update Week of April 17, 2017

We are about to start major construction work at Charlottetown Centre East wing and West wing. All of the windows will be replaced. As well the exterior masonry will be repointed and window lintels replaced on the top floor windows.

The general plan is to focus initially at the East wing and move to the West wing. At times the work will be noisy.

The masonry contractor is West Masonry. They will be on site starting Tuesday April 18. The first few days will be setting up staging. We will endevour to minimize disruption during class time between now until the end of the normal school year (April 30).
The window contractor is O’Connor Glass and window installation will start early May.

We need to start the work at these times in order to achieve our schedule goals of having all the work complete before the start of the September school year.

Please keep windows closed during the construction activity.

Note: there will not be any window or masonry work happening at the central wing (CLFI) however it may be noisy at times when construction activity is happening in adjacent areas.

This is an important project for Charlottetown Centre and we thank you for your cooperation